Calendar Days do not match Calendar Hours?

3 replies [Last post]
Rodney Jones
User offline. Last seen 43 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi,

 

I have a calendar running 10 hours per day, 5 days per week. It is assigned as the Activity default calendar. When I create a new activity with a duration of 3 days and then change my User Preference to show Duration in Hours, the hours are only 24 but I expected them to be 30.

 

Why is this happenning? 3 days on a 10 hour per day calendar should be 30 hours but it appears to be referencing an 8 hour day.

 

You help would be greatly appreciated.

 

Rod

Replies

Rodney Jones
User offline. Last seen 43 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Brilliant, Yes, it was the Timeperiods.

 

Thanks.

 

Rod

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you have not set the hours correctly or have not set the correct default calendar  

David Kelly
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days