How to Close One Project on P6

Dear Member, 

So I recently faced this problem while working with two projects opened at the same time. How can I close only one project if multiple projects are open? I usually use the Ctrl+W shortcut which closes all project. Please share your experience?

 

thanks, 

S
Santosh Bhat 👤 Member for 21 years 2 months

Return to the project view click on only the project you want to open, right click mose and select OPEN. This way you don't need to close all.