How to add 50 labours to one activity?

1 reply [Last post]
walid Lahiani
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Hello

Imagine we have a task which original duration equal to 7 days

one labour work 10h/day

If I add this labour to the activity the Budget unit become 70=10h*7days

If I want  50 labours working on this activity I have to change the budget unit to 10hx7daysx50labours=3500 isn't it?

Thank you

Replies

niles luo
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None

hi,

  I think it is.

Best Regards.