Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

the case for and against putting a Float Activity at the end to keep critical path zero for simplicity etc.

1 reply [Last post]
John Reeves
User offline. Last seen 21 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None
In an normal environment with an Owner, a CM, and a Contractor what is the the case for and against putting a Float Activity at the end to keep critical path zero for simplicity etc and to key on time left at the end.  The definition of Ctitical Path is zero float - but what if you have more time than you need - such as 3 months on a 2 year job, it would not be helpful to inflate durations just to hit the spec, but also a "float" activity at the end might have issues.  If the contractor wants to show float, isn't it in the owners favor to let them. 

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

why not just set the threshold and define the critical path to what ever float that you have  

go to tools

schedule 

options

Define critical activities as 

Total float less than or equal to 

then put in your value.

the other option is to never set a project must finish by date or have a fnish on or before milestone this way the float wil ALWAYS be zero