Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Roll Up Performance % Complete

1 reply [Last post]
Emma Lang
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

I have some activities with zero resources against them. Basically a manufacture line, which I put a % complete against. I would like this to roll up to the summary level. 

Is this possible to do in P6? I've tried changing the % complete type. even using a dummy resource. But it doesn't seem to roll up. 

 

Any suggestions?

Replies

Zoltan Palffy
User offline. Last seen 26 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete