Physical Percent Complete Roll up

3 replies [Last post]
Riyadh Yahia
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 62

Hi Friends,

Is there any way around to have Physical Percent Complete Roll up at the top, the same way of Performance Percent Complete?

Regards to All

Riad

Replies

Jash Sales
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None

Hi Arun,

In my opinion,the performance % complete is used in computing the earned value by multiplying to BAC. Perfomance % complete is calculated in different ways depending on the nature of work and this will be set-up and agreed by both parties(client and contractor) during the preliminary stage of the project, to be used in evaluating the progress of work. This can be equal also to physical % complete if you have chosen as an activity % complete type in calculating it. While the physical % complete is just the %age of work done physically.

Hope this will clear your question.

Regards,

Jash  

Arun Vasanth
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Hai Friends Please Differntiate between Performane percentage & Physical percentage....... Regards Arun
Jash Sales
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None

Hi Riad,

 

Physical % complete can't be rolled up as it is inputed manually to individual activities or by assigning steps in calculating it.

Performance % complete can be rolled up by assigning cost to each activities as this is related to cost in computing your earned value and this will be computed based on the assigned activity % complete type.

Regards,

Jash