Performance Percentage Completion ?

2 replies [Last post]
mostafa yousef
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 18 Feb 2017
Posts: 3
Groups: None

Hi, 

Performance percentage completion: On updating the P6 Program of works monthly (Jan 2017 to Feb 2017)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

Regards,

Jossef

Replies

mostafa yousef
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 18 Feb 2017
Posts: 3
Groups: None

Thanks alot Kannan. As you said there was increment in the budget. 

 

Problem is now resolved. 

 

Thanks

Kannan CP
User offline. Last seen 1 year 6 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mostafa,

Make sure that your Total Budgeted Cost is not increased. Also check if the previous month progress for any of the activities is reduced, as a correction.

Best Regards

Kannan