Finding Slipping and Not started activity compare to baseline filter

1 reply [Last post]
Nathan Siva
User offline. Last seen 19 weeks 1 day ago. Offline
Joined: 28 Apr 2014
Posts: 30
Groups: None

Hi All,

How to identify the not started activity and slipping or negative variance activity compared to baseline using filter.

Replies

Zoltan Palffy
User offline. Last seen 12 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

add a column look under duration and add Variance - BL1 Start Date