Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Create a Filter that show activities with no baseline

3 replies [Last post]
Mike planner
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hi, 

 

I want identify all the new activities i added to my original programme. 

In order to do that, i think i need to create a filter that shows all the activities with no baseline but i cannot find a solution. 

How do i create a filter that show all the activities with no baseline?

 

Thanks

Mike  

Replies

Mike planner
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Thank you so much!

 

Mike 

Rafael Davila
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Also of interest is when I need to identify and show all activities in compared schedule but absent in current version.

Absent-in-compared-schedules-Gantt

Santosh Bhat
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Use a filter with condition "Where BL Project Start (or BL Project Finish) Equals" and leave the value field blank.