Filter activities that has changed compared to assigned basline

5 replies [Last post]
Håkon Haukebøe
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 18 Sep 2012
Posts: 25
Groups: None

Hi all. Does anyone know how to create a filter wich only shows the activities that has changed (start or finish) in current plan compared to assigned baseline?

 

cheers

 

Haakon

Replies

Håkon Haukebøe
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 18 Sep 2012
Posts: 25
Groups: None

thanx alot.

 

Haakon

Arnold Puy
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Hakon,

Check this out

1741
added_new_activities.png

 

 

 

 

 

 

 

 

 

 

 

 

 

1742
added_new_activities-1.png

 

 

Cheers,

Arnold

Håkon Haukebøe
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 18 Sep 2012
Posts: 25
Groups: None

Thanx, that works. Only thing i miss is that new activities (activities not in baseline, but in current project) seem to fall out. How can I include them?

muhammad anwar
User offline. Last seen 5 years 13 hours ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS

Haakon

 

Filter on Baseline Start or Finish Variance

 

Regards

Gary Whitehead
User offline. Last seen 6 years 5 weeks ago. Offline

Filter on:

 

Where Variance - BL Project Finish date is not equal to 0

Or Variance - BL Project Start date is not equal to 0 

 

 

Cheers,


G