% Planned complete

5 replies [Last post]
Nouraldin Alqudsi
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 15 Oct 2016
Posts: 6
Groups: None

Hello Dears;

When we do the monthly report, we usually send to the contractor a table showing the most important zones which have the activities of the project; showing in this table:

1- % Planned complete

2- % Actual complete

3- Variance; (Actual % - Planned %)

No problem with getting the actual %, my question is how to get the planned %

Please Help :)

 

Thank You,

Replies

Domingo Bonaobra
User offline. Last seen 1 year 6 weeks ago. Offline

Hi Nouraldi, Hope this will answer more on your questions.. https://www.planacademy.com/primavera-p6-schedule-percent-complete-guide-2/ Good Luck!!!

Nouraldin Alqudsi
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 15 Oct 2016
Posts: 6
Groups: None

Hi Sir,

The resources are loaded,

Actually i tried the same on another project, and the percentages for the WBS's were calculated

Is there any relation between kind of resource ( which i dont know what is it ) and the shedule % ?

Best Regards

Domingo Bonaobra
User offline. Last seen 1 year 6 weeks ago. Offline

Hi Nouraldi,

1. Yes, you got it.

2. Seems your schedule was not resource loaded?

Please let me know.

Nouraldin Alqudsi
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 15 Oct 2016
Posts: 6
Groups: None

Hello sir;

Does this picture describe your answer?

and why the WBS has no planned (Schedule) Percent ?

or i should estimate it?

Thanks for your help :)

4480
untitled.png

Domingo Bonaobra
User offline. Last seen 1 year 6 weeks ago. Offline

Hi Nouraldi,

To be able to show the % Planned Complete ( Schedule % Complete in Primavera ), you should maintain and assign baseline to your current schedule.

Hope this helps.