Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

XER import error from P6 8.3 to P6 Professional R15.2 without error notification

6 replies [Last post]
oriol manich
User offline. Last seen 8 years 47 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Hello folks,

I have a really weird issue. While importing a XER file to Primavera P6 Professional R15.2 (the XER file obtained from an online P6 8.3 through a CITRIX RECEIVER platform) the import process starts with the loading and suddenly stops, with no error or exception window popping up.

I have no clue about the cause.

Can anyone help?

Thanks.

Regards,

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

robert make sure that you have the proper rights set on your laptop

Robert Varghees
User offline. Last seen 7 years 6 weeks ago. Offline

IMPORT ERROR in 15.1 version p6

 

Hi, i am importing .xer from 15.1version to my laptop but i am unable to retrive my cost and budgeted units . Since both are same version why i am getting error. Could anybody can help. I have tried to import why XML format also and gave error with log details.

please help if any bodyhave encountered same problem.

Thanks & Regards

RV

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

use the p6 excel parser and bring it into the parser then rebuld the xer file in the parser

here is the link to the parse

https://www.planacademy.com/how-to-clean-an-xer-file-using-the-parser/

https://planacademy-nffybkc1gjvuuhit.netdna-ssl.com/wp-content/uploads/2012/01/xerFileParserBuilder_2007.xlsm

 

Dear all,

 

I have problem in importing xer p6 file.

Error occur "CVRCU-1939-9  Default value  provided for field ev_compute_type is not valid"

Waiting for your inputs.

 

COCOY

oriol manich
User offline. Last seen 8 years 47 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Hello Zoltan,

I already tried and also a colleague imported that same file successfuly so we ruled out that the file is corrupt.

Thanks

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

down load the xer from the citrix server agian it may be corrupt