Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

1 day duration - finish day is different from Start day

1 reply [Last post]
Steve Scheduler
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 13 Apr 2016
Posts: 3
Groups: None

This may be a simple question but why if a task has a 1 day duration (8 hous) is the finish day the next day, e.g.

 

Start day - 4/13/2016 - duration 1 day == finish day is 4/14/2016.  Logic tells me that the finish day is 4/13/2016.  

 

Is there a way to show the real finish day without changine the duration to 0?

 

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you may not realize it but Primavera uses hours even though your planning unit is in days. 

your times are incorrect and possibly your remaining durations are not in whole number of days especially if you are using duration % complete to calculate the remaking durations

here is the fix

go to edit users preferences

date tab

on bottom show minutes and check 12 hour

next go to your project directory highlight your project click on your Planned Start Date make sure that the TIME is 8:00 am or the earliest time setup in all of your calendars that you are using for that project.

Next click on your must finish by date and make sure that the TIME is 5:00 pm or the latest time setup in all of your calendars that you are using for that project.

Next click on the data date make sure that the TIME is 8:00 am or the earliest time setup in all of your calendars that you are using for that project.

now for any start milestone constraints make sure that the TIME is 8:00 am or the earliest time setup in all of your calendars that you are using for that project.

now for any finish milestones make sure that the TIME is 5:00 pm or the latest time setup in all of your calendars that you are using for that project.

now for any activities in progress meaning started but not complete make sure that the actual start date is  TIME is 8:00 am or the earliest time setup in all of your calendars that you are using for that project.

go to edit users preferences

click on the TIME Units tabs

under Durations Format change the decimals form 0 to 2.

now look for any activities that are in progress meaning started but not complete make sure that the remining duration is in whole numbers not fractions.

press F9 recalculate your schedule now a one day activity should only span one day NOT 2.

now when updating make any actual start times  8:00 am and actual finish times 5:00 pm and make sure that the remaining durations are in whole numbers.