Percentage complete

1 reply [Last post]
leighton rogers
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 9 Jan 2016
Posts: 15
Groups: None

Hi all

Ill give you a scenario.

i have an activity which has 800 man hours budgeted for it and say i have done 400 hours is there any way i can add the hours in so it will change the physical % complete automaticly?

 

Sorry for the simple questions im new to this game.

 

regards

 

L8S

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

change the duration type to units