WBS Start and Finish Date in P6 schedule

2 replies [Last post]
Vignesh S
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

Anyone Kindly guide me on how to display start and finish date at WBS lvl in P6 schedule printout.

Replies

Vignesh S
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

Thanks Jerome,that worked out nice

Jerome Odeh
User offline. Last seen 6 weeks 2 days ago. Offline
Joined: 19 Jan 2004
Posts: 105

Vignesh,

From your menu bar, click on View > Group & Sort and in the Group & Sort dialog box, tick "Show Group Totals" check box under Display Options. Click Apply and then OK.

 

=jerome