Trouble MSP XML import to 8.3.2

1 reply [Last post]
Sander Gorissen
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 10
Groups: None

Hi all! 

Me and my team are running into some trouble when trying to import a XML file from MSP 2010, into P6 8.3.2 professional. 

Somehow, it looks like primavera is doing it's job, but when ready, the schedule is nowhere to be found in the EPS overview (no fitering on EPS). Then if you try again (without rebooting), primavera keeps kicking me out of the import options. 

Anyone else has had the same issue? 

thanks in advance!

Sander G.

Replies

Sander Gorissen
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 10
Groups: None

Yes, Primaned found the solution!

Issue was in MS project with options-->Schedule-->Calendar options. MSP indicated 31 days per month ... Primavera can only handle 30 days a month ... 

Quick fix, if you did any research, thanks! 

Sander G.