Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Having trouble replicating P6 schedule after import

1 reply [Last post]
Teague K
User offline. Last seen 13 years 36 weeks ago. Offline
Joined: 10 Nov 2008
Posts: 9
Groups: None

All,
I am managing a fabrication subcontractor who is delivering weekly schedule updates to me in a PDF and P6 XER file.

I import the P6 file into my P6 software in a new EPS node with only this single project in the node. I use the "update existing" setting for all the project fields during the import. (not that this matters because I am not updating an existing project). I then open the project file and I am not able to replicate the same dates that are shown in the PDF file that I am provided with the P6 file.

The activities that I show in my Primavera differ only slightly, 1 day on many activities. This leads me to believe it might have something to do with the work calendar settings and the number of hours per week that I have in my software compare to the software settings of the subcontractor's Primavera. (if he is using a 10 hour day and I have an 8 hour day, my software will bump activity finish dates to the next day or multiple days in some cases)

What information should I ask for, from my subcontractor, to make sure I have all the calendar and work hour settings correct? He can take some screenshots and send them to me.

If my problem and question are not clear, let me know.

Replies

Ferdinand U.
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
Show time in pdf dates Also calendar setting as you point out