Trouble Importing XLSX

1 reply [Last post]
Romeu Oliveira Jú...
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 11 Jan 2006
Posts: 5
Groups: None

Hello there!

I am having issues while importing units and durations on P6, using XLSX files. 

When I import floating point values, it ignores the decimal point and import as an integer. For example, importing 12.05 and it writes 1,205 in the database. 

Does anybody have any idea on why does it happen and how to fix it?

I tried the oracle support here in Brazil but the company analysts only search the knowledge base and send default answers and workarounds that generally don't work. 

I am using P6 PRofessional R16.2 Release 16.2.7 (Build #: 23684).

Thank you!!!

 

Replies

Zoltan Palffy
User offline. Last seen 14 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

is the excel fields formatted correctly does it start with an `