Hi all,
I'm looking to produce s-curves using Primavera, so far it's ok.
But then, when I display the cumulative curves for budgeted, actual and remaining activities, the bugeted one shows as it should, the remaining one shows as well, but the actual units line doesn't show. I only get a flat blue line at 0 and from the day of the data date, nothing showing before that date, so I have nothing for what has happened in the past and got completed.
I don't understand why it won't show it... Can you please give advice on how I can make it appear right?
It is the same when I display the by date bars, the budgeted ones show for the period of time before the data date but the completed activities don't show at all (as actual or something else).
It might be a really basic thing but I can't seem to fix it. Has anyone had the same problem and how did you resolve it?
Thanks :)
Replies