hi guys first of all sorry for my bad english i hope u understand.
in my schedule i have more than 2000 activities.i added wbs summary activity for each wbs.then i assigned budgeted (contrac price) and actual cost.some activities finished and some activities still on going.but i couldnt get s-curve how i want.s curve is here.whts the problem how can i solve this.please help

Can you send the XER file to my email [email protected]
I will check on another version and will let you know the outcome.
hi all
i m using 6.0 version of primavera.
Hi Ferhat
Have a look at Project Tracker, it creates S curves directly from P6 without the need to export the data to a spreadsheet. You can get a free trial and more product infromation at www.willmer.co.uk
What version of P6 are you using? I had similar problem when I was using P6 6.2, after I switched to version 7 it was solved.