to display resources in the gant chart

2 replies [Last post]
amar iadaden
User offline. Last seen 10 years 1 day ago. Offline
Joined: 24 Mar 2011
Posts: 3

I am a new user in primavera p6, please can some one to show me how to display on the gant chart the resources assigned for each activity beside the bar.

Thank you

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

that is incorrect you do not need to make a udf 

just go to the bars and select current bar labels 

then click on the bar lables tab

then select add 

then in the position select right 

clikc in the label area look in the drop down and select budget labor units for rmanhours or budget labor cost or whatever you want to show there

Raymund de Laza
User offline. Last seen 42 weeks 21 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Amar,

Copy the Resources into a UDF then use it as Bar Label.

 

Regards,