Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to display individual resource assignments in Activity View Gantt chart

No replies
Rodney Jones
User offline. Last seen 1 year 1 week ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Everyone,

 

Has anyone found a way to display individual resource assignments in Activity View Gantt chart?

 

I have Group & Sort as by Resource, but activities that have multiple resources are grouped together as if they were a single resource. Is it possible to Group the individual assignments in the Activity Tab?

 

Rod

Rafael Davila
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Spatial resources cannot be modeled as Renewable Resources. Spatial resources we model as consumable resources, therefore we track them using Materials Gantt.

Rafael Davila
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Materials are consumable resources that must be available ("leveled") in order for the schedule to be viable. If materials become depleted activities can be interrupted until more become available.

Material Gantt among other things can show:

  • the activities for each material as well as the activity interruptions
  • diagrams that show inventories level and materials consumption rate
  • parameter values for materials available in this view but not in Activity Gantt.

2022-10-22-08-09-18

Rarely my jobs are limited by materials to the point materials leveling is necessary.  In rare ocassions when materials must be leveled in our jobs these are frequently a driving constraint. It may seem an exageration to level materials easily available such as cement and sand but in remote location these can become critical.

2022-10-22-17-05-43

david kelly
User offline. Last seen 1 week 1 day ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

You could use Primavera P3 from about 1985 ?

 

You could:

 

Export a spreadsheet with the Activities sheet which has an extra blank text UDF, and the Resource Assignments

Concatenate the resource assigments into the Activity Sheet UDF

Import the spreadsheet

Use the UDF as a barchart label

Luckily, offspring #4 is an Excel guru, and I get this stuff done very quickly!

david kelly
User offline. Last seen 1 week 1 day ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

You could use Primavera P3 from about 1985 ?

 

You could:

 

Export a spreadsheet with the Activities sheet which has an extra blank text UDF, and the Resource Assignments

Concatenate the resource assigments into the Activity Sheet UDF

Import the spreadsheet

Use the UDF as a barchart label

Luckily, offspring #4 is an Excel guru, and I get this stuff done very quickly!

Alex Lyaschenko
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

Rodney,

As a list, it could be done via Resource Assignments. Santosh explained it well.  If you ask about the resource Gantt Chart, Primavera can't do it. You need to export your schedule to another tool. At least Spider Project has Resource Gannt

https://saluteenterprises.com.au/spider-project-product/spider-project-advanced-resource-modelling/

Santosh Bhat
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Not in the Activity Tab, but this can be done in the Resource Assignments view.

Think of it this way:

  • In Activity View, each activity is only displayed once, 
  • In Resource assignments view, each resource assignment is only displayed once, 

And in the Assignments view, you have options to group, sort filter and display columns just like in the activity view (

You can see what can be presented on this page I wrote some time ago: Primavera P6 Views and Layouts | Australasian Project Planning (austprojplan.com.au)