Importing an xer filefrom V7 to V8, resources are missing.....anyone know the answer?

4 replies [Last post]
doyin mcarthur
User offline. Last seen 4 years 21 weeks ago. Offline
Joined: 13 Oct 2003
Posts: 14
Groups: None

I have just upgraded to P6.8.2 however our contractor is using P6.v7, when they send me an xer file and I import this I show only about a quarter of the resources that they have.  I have tried importing by insert new and also update resources but no difference.

Does anyone know how to solve this issue?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that your admin preferences has the rights to do this

efren labay
User offline. Last seen 10 years 6 weeks ago. Offline
Joined: 26 Dec 2006
Posts: 12

Hi,

 

Can anyone send me a working P6xerFileParserBuilder.

I have some problems of import/export.

 

This is my email add: EFRENDLLABAY@YAHOO.COM

 

Thanks & Appreciated.

 

EFREN

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Double sorry!

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Doyin

Did you check:

- The xer-file - you can open a copy with any editor: can you find the resources?

- The import ends with a log-file; what does it say?

- Do you have sufficient access rights to add new resources?

- Your import options

Good luck!

Dieter