Problem in material resource budgeted units after importing xer file

5 replies [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Hi Everyone, 

i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?

unit price is not zero and calculate cost from units is checked

Best regards,

Replies

MK TSE
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None

What setting (resource and cost related fields) is selected on Import template?

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

also check your duration type make sure it is set to fixed duration & units/time for each activity 

Kari Lucas
User offline. Last seen 4 years 46 weeks ago. Offline
Joined: 18 Jun 2010
Posts: 16
Groups: None

I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

uncheck calculate costs from units 

Casey F
User offline. Last seen 2 years 48 weeks ago. Offline
Joined: 28 May 2016
Posts: 17
I am having the same issue. I loose the budget units when importing, but not consistently. About a quarter of the resources maintain their budgeted units. I am running 17.8 exporting as 8.2 per customer requirements.