Importing an xer filefrom V7 to V8, resources are missing.....anyone know the answer?

1 reply [Last post]
doyin mcarthur
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 13 Oct 2003
Posts: 14
Groups: None

I have just upgraded to P6.8.2 however our contractor is using P6.v7, when they send me an xer file and I import this I show only about a quarter of the resources that they have.  I have tried importing by insert new and also update resources but no difference.

Does anyone know how to solve this issue?

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

do you have the rights to import the resources and have you checked insert new for the resource during the import process ?