Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Exporting Relationships to Excel

1 reply [Last post]
Robert McGhee
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 27 Mar 2008
Posts: 15
Groups: None

When exporting activity relationships to Excel, only get 10 characters in the predecessor & successor activity names, but when I export activities, get the entire name.   How do I expand the number of characters in the relationships export?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 14 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

one thing to do it to create a Vlookup in the TASKPRED tab that references the TASK tab in excel.