Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Leveling Priority

1 reply [Last post]
Harold Forsberg
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 15 Aug 2001
Posts: 20
Groups: None

I have a schedule with a concrete resource loaded agaianst several hundred activities.  The concrete activties have been prioritized using the "Activity Leveling Priority".  When viewing the Resource Assignment screen, I used to be able to group by the "Activity Leveling Priority" but this option appears to have disappeared.

I have tried to run the P6 repair program from the Windows Control Panel, but since this version was installed by the vendor, I =nver received the installation cd.

Any suggestions on how to get my resources grouped by the "Activity Leveling Priority"

 

Tnaks in adavnce for any help

 

Replies

Raymund de Laza
User offline. Last seen 26 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Harold,

Activity Leveling Priority data can be viewed only from the Activity Pane.

 

Regards,