Percentage complete type on P6

2 replies [Last post]
Saqib Ali
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 26 Jun 2012
Posts: 6
Groups: None

Hello Planner's,

How are u?

I'm searching the definition & diference between percentage complete like Duration per%, Unit Per%, Phisycal Per%, Performance per% & Schedule percentage. what the effect of these percentage on schedule & where were we use it.

 

Many Thanks

Saqib Ali

Replies

Saqib Ali
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 26 Jun 2012
Posts: 6
Groups: None

Thank Manochehr Hosseini for this helping link but this link not opened my window when i opened it show me the Page not Found message.

 

my second question if we making Revenue Curve and we have the project BOQ. Then how will we achieved the planned amount for every month remaining the project duration. 