Physical Percentage Progress type and Actual Units

2 replies [Last post]
Kannan CP
User offline. Last seen 1 year 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

While using the Physical Percent Complete, the actual units is not getting updated automatically during the progress update(activity % complete). If duration percent complete is used, actual units will be updated automatically.

Is there any option to get the actual units updated automatically, using the physical % complete. The tab of " Auto Compute Actuals" is on.

Regards

Kannan

Replies

Kannan CP
User offline. Last seen 1 year 2 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Dieter..

Dieter Wambach
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi Kannan

As follows is from the P6 RefManual Chapter 4:

"Update activities with Physical percent complete type

In the Activities window, select the activity to update and display the Activity Details Status tab. Enter the physical percent complete and the remaining duration for the activity. If resources are assigned, you must also update each resource’s actual regular units. "

Hope this helps.

Regards

Dieter