Percentage type in P6

No replies
Kannan CP
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Guys,

Which one is the most reliable selection for percentage complete in P6. Duration, Physical or Units.

In my opnion selction of "Units" is good, because the labour units will be updated automatically for the percentage we input.

For the "physical" type, labour units will not be updated automatically and this to be done manually.

For the "duration" type, remaining forecast duration and % complete may not match. So it will affect the labour units as well.

Above is my understanding. Kindly input your opinion based on experiences.

 

Thanks in advance

Kannan