Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

difrence between orignal duration & at completion duration

2 replies [Last post]
rizwan khan
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 28 Aug 2012
Posts: 11
Groups: None

Dear all

 I had problem with the duration which i was working , there is 

 

 

 

what is diffrence between orignal and at copletion duration , how we can use it  in primevera 

thanks you all

Replies

Arnold Puy
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Rizwan,

The Original duration is the number of working days required to complete each activity based on the current schedule. However, At completion duration is the sum of the actual duration and the remaining duration.

Cheers,

Arnold

rajesh kumar
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 14 May 2013
Posts: 3
Groups: None

hi

Orginal Duration -planned duration 

at cmpt duration nothing but  actua work performed during project