Hi Professionals, (I want everybody input please)
My Question Is Very Simple But, I Have A Confusion Please Help Me Out In It.
Because Of It I Destroyed My Approved Baseline Programmed.
Given Below Settings I Mostly Used in P6.
Duration Type = Fixed Duration & Units.
% Complete = Duration % Complete Type.
1) Please Guide Me First In The Very Beginning When I Add A New Project In The Project Window For The Preparation Of Baseline Of Any Project Which Settings I Have To Adopt Compatible With (Duration % Complete Type & Fixed Duration & Units).
For Example:
In Project Window For
Calculation Tab= Which Settings I Have To Adopt……….? Compatible With (Duration % Complete Type & Fixed Duration & Units).
Default Tab= Which Settings I Have To Adopt……….? Compatible With (Duration % Complete Type & Fixed Duration & Units), Etc…………..
2) Which Settings I Have To Keep In Mind When I Go In The Activity Window Of Any Project Compatible With (Duration % Complete Type & Fixed Duration & Units).
For Example:
In Activity Window For
Resource Tab= Which Settings I Have To Adopt Regarding Labor Resource……….? Compatible With (Duration % Complete Type & Fixed Duration & Units).
3) Which Settings I Have To Keep In Mind When I Go In The Resource Window Compatible With (Duration % Complete Type & Fixed Duration & Units).
For Example:
In Resource Window For
Default Tab= Which Settings I Have To Adopt……….? Compatible With (Duration % Complete Type & Fixed Duration & Units), Etc…………..
Replies