Need Help with Event Code: 90C0432B During Baseline Updates

J
JJ Aucoin 👤 Member for 23 years 11 months

Hello fellow P6 gurus,

Can you assist me with my latest P6 issue??

Need Help with Event Code: 90C0432B    I keep getting this error message during my baseline updates.   Each time I press "Update" I get this message before it runs.

Trying to update my baseline to mirror the projects actual dates.

 

thanks,

L
Larry Cortez 👤 Member for 13 years 5 months

Is this standalone or client-server?

Try going into C:\Program Files (x86)\Common Files\Primavera Common\Java and run the admin.cmd utility. Log in with privuser. In the window that opens, right-click on the INTERNAL_PLUGINS configuration and click Delete. Save and exit the utility. Close and relaunch Primavera and try running baseline update again.

Let me know if this works for you.

 

Regards,

Larry

litbusiness.com

R
Raymund de Laza 👤 Member for 16 years 7 months

Hello P6 Users,

I encountered the same error and still was not able to sort out.

Anybody has the solution?

 

 

Regards,

Forum Sponsor

Top Posters

Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts