Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Monte Carlo Risk Analysis

6 replies [Last post]
Hermie LaO
User offline. Last seen 17 years 40 weeks ago. Offline
Joined: 27 Jan 2005
Posts: 29
Groups: None

Correction! This is a methodology NOT a product!!!

Open has this built in as a scheduling functionality.

Replies

Mehdi Rashidi Ala...
User offline. Last seen 9 weeks 4 days ago. Offline
Open Plan was capable of quick Monte Carlo simulations, and gave detailed information regarding our activities’ early and late dates
ashraf alawady
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 26 Aug 2006
Posts: 320
Groups: None
Hi
you can get the neccesary information by reading ’PMBOK’book (Project Management Body Of Knowledge)or visit the website of the project management institute at www.pmi.org.
Good Luck
Sai Prasad
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 18 Apr 2005
Posts: 6
Groups: None
Thank Benard
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
You can read about Monte Carlo Risk Analysis in Chris Hendrickson’s on-line book Project Management for Construction: Scheduling with Uncertain Durations

There are several discussions in the Schedule Risk and Schedule Risk Analysis forum regarding Monte Carlo.

Bernard Ertl
eTaskMaker Project Planning Software
Hermie LaO
User offline. Last seen 17 years 40 weeks ago. Offline
Joined: 27 Jan 2005
Posts: 29
Groups: None
Hi Sai,

Basically, Monte Carlo Analysis allows you to enter Optemistic/Most Likely/Pessimistic durations on activities. You then identify the task you wish to evaluate(ie project/milestone completion activity).

You then run iterations where the system computes different combinations using programme logic and duration combinations.

End result would be a % likely completion of the identified milestones and completion dates.

Regards,

Hermi
Sai Prasad
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 18 Apr 2005
Posts: 6
Groups: None
Hi
Please let me know what is this Monte Carlo Risk Anlysis & where do I get to learn this methodology
regards
sAI