Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Monte Carlo Simulation Challenges

2 replies [Last post]
Alex Lyaschenko
User offline. Last seen 10 weeks 12 hours ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None
Risk simulation is becoming popular but most risk simulation tools and the ways how they are used miss some important functionalities that make the results of this simulation unreliable.I am continuing my posts about 'Monte Carlo Simulation Challenges':

N1: Monte Carlo Simulation Challenges - Salute Enterprises

N2: Monte Carlo Simulation Challenges. Simplicity Challenge. - Salute Enterprises

N3: Implementation of the Critical Path Methods in Different Scheduling Tools - Salute Enterprises

N4: Monte Carlo Simulation Challenges. Distribution Shapes Challenge. - Salute Enterprises

N5: Monte Carlo Simulation Challenges. Critical Path Volatility Challenge. - Salute Enterprises

N6: Monte Carlo Simulation challenges. Level of details challenge. - Salute Enterprises

 

What other MCS challenges that need to be discussed?

 

Regards,

Alex Lyaschenko

Alex Lyaschenko | LinkedIn

Replies

Alex Lyaschenko
User offline. Last seen 10 weeks 12 hours ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

Hi Peter, 

Sorry for delay with th response.
>1 quality of data assumptions - are we all biased in some way?

 Yes, and there are methods to deal with it. 

>2 how to get a collective team risk effort rather than risk manager / software

The schedule development process need to be changed. Initial data has to be collected as a range with primary uncertainties from SMEs. Risk managers have to support that and use collected data for analysis.

> 3 "selling" results to senior management in a meaningful way - is it just contingency drawdown?

It is a risk transfer. Senior management can decide to start the project even if it is only, let say 10% to meet dates and cost commitments. The PMs can do their best, but there is a 90% chance that they ask extra time, money or both.
 

> 4 how do we deal with external project events not explicitily covered in the contract (which seem to becoming more common)

All external dependencies is a specific type of risks and must be managed via risk processes. 

Technically, in a risk simulation tool, create an external task, not a milestone (as it has no duration). Simulate the duration uncertainty of this task. I will cover it the future posts.   

>5 next simple steps beyond MCS for more real world scenario
Learn MCS “side effects” and alternative approaches, like “3 scenarios” method. 

Peter Holroyd
User offline. Last seen 2 days 7 hours ago. Offline
Joined: 6 Jun 2005
Posts: 166

Alex,

1 quality of data assumptions - are we all biased in some way?

2 how to get a collective team risk effort rather than risk manager / software

3 "selling" results to senior management in a meaningful way - is it just contingency drawdown?

4 how do we deal with external project events not explicitily covered in the contract (which seem to becoming more common)

5 next simple steps beyond MCS for more real world scenario

 

Peter