Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Gant baseline and actual date icons for each task

2 replies [Last post]
Joshua Topham
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 6 Nov 2019
Posts: 4
Groups: None
Hi, I have a very basic project with a list of milestones, all of which had baseline dates. For some milestones the baseline wasn't hit and we have later actual dates in another column. (Where there's no slip the baseline and actual columns have the same date.) I'd really like to visualize this on the gant with a baseline icon as well as the actual one so the missed milestones were easy to see. Does anyone know if it's possible to add a second date icon to the gant view like this?

Replies

Santosh Bhat
User offline. Last seen 26 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Joshua,

Where you select bars, you need to create a new one that uses the BL Project Start and BL Project Finish date fields and it will display the dates from whichever project you have assigned as the "Project Baseline" in the Assign Baselines option.

Rodel Marasigan
User offline. Last seen 1 day 15 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Just create another milestone on Bar Style format using Actual Start and Actual Finish.