Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

schedule tasks by date and time

1 reply [Last post]
mike soha
User offline. Last seen 17 years 13 weeks ago. Offline
Joined: 24 Aug 2007
Posts: 3
Groups: None
i’m new to project; just a couple days into it actually - what i’m trying to do is schedule a reoccuring task specific to date and time. by date is easy enough, but i want it to start at 9:30 am and end at 10:00 am.

i also notice that task itself will show the duration in outline level 1 as 8hrs long when the duration in outline level 2 shows the duration as .5hrs; why is it doing this?

thanks for any thoughts/relies

Replies

L.E.N. Lewis
User offline. Last seen 2 years 31 weeks ago. Offline
Joined: 2 Aug 2007
Posts: 47
Groups: None
To schedule a recurring task to a specific time:

1. Tools | Options | View-tab and set "Date Format" to an item that shows the time.

2. Insert | Recurring task... enter the task name; set the duration to 0.5h; use the calendar to select the date for the first occurrance; overtype the default start time with your 9:30AM start time; click OK.

As for your duration issue, the duration of a sub-task is the duration for the task; the duration of a summary task is the elapsed duration from the start of the earliest sub-task to the finish of the last sub-task.