I need to set up a schedule say with 100 tasks and 10 resources the tasks will last for a whole year (fiscal), I would like the start and finish dates to remain constatnt for all tasks within the schedule, also I do not know which team members will be working on any of the tasks up front, they may all do some work on each task sometime within the year time frame, but being in the enterprise environment I want all tasks to show up on all time sheets to enable any team member to log time against any task.
The way I am thinking to set the tasks up would be.
Fixed Duration
Non Effort driven
As Late As Possible constraint
Add all team members to all tasks at zero Units.
I realize the resource allocation will not be very useful as all team members will show as available when I know they are really not, but can any of you think of anything else that I may have missed, or a better way to set it up?
It is basically only for capturing actual time worked, but would still like to see the Gantt chart reflect time logged.
Thanks GM
Replies