Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Work progress at status date

15 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello Planners and MSP specialists,

How could it be possible to make MS Project compute the percentage between actual work and theoritical work at the status date?

One 5 day task starting Monday

Two resources assigned to this task: R1 is working 10 hours / day; R2 is working 8 hours / day

Status date is Wednesday night

R1 has worked 10 hours on Monday, 9 on Tuesday, 8 on Wednesday, or 27 hours

R2 has worked 5 hours on Monday, 4 on Tuesday, 3 on Wednesday, or 12 hours

Is it possible to get MSP compute that R1 has worked (10+09+08)/(10+10+10) = 90% and R2 has worked (05+04+03)/(08+08+08) = 50%  

Thanks for your help

Alexandre

Replies

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Jerome,

I do not use MSP but it looks like you got it, you are very good at MSP. I use external file hosting for my pictures as my experience has been that figures stored at PP tend to get lost. I use Photobucket, is free. Your postings shall be available for future reference by users of MSP, I find them very valuable.

I believe it might be you can even improve on your formulas if using user defined field to define some of the values, but this requires someone with your knowledge of MSP.

I do not find MSP to be bad software, on the contrary it can do many things P6 cannot do, one of the things I will like to explore with you is the ability to model Spatial Resources using MSP resource leveling on hammocks, something P6 cannot do.

Best Regards,

Rafael

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Alexandre,

At home contractors do not keep detailed cost tracking via the schedule, for this we use our Unit Costing system integrated with our accounting system. Here we catch up every expense up to the cent. We also track production or volume of work along with effort, something MSP cannot differentiate, it cannot even understand resource production rates.

http://www.foundationsoft.com/unit-cost-production-reporting/

We do not use mere budgeting without tracking volume of work. We do not use EVM unless required by Contract. I consider EVM flawed Budgeting with regard to schedule, the literature with this regard is huge. A strong statement for a few ladies that blindly advocate for EVM. We also avoid tracking billings with the schedule, see next reference.

http://www.nflaace.org/index_files/john_orr_cost_loaded_schedule_updatin...

We do not find detailed labor tracking using the CPM practical. At times a few resources work overtime on a few days, at other times a few resources not in the resource plan work on some activities. Trying to input all these variants into a schedule update is a nightmare. To this you must add all materials, subcontracts and all everyday expenses. Then you must add on periodic interval the production rates as to get the unit costing. For tracking of detailed labor cost we not only use our unit costing but also the payroll reports.

At home we use the schedule for planning future work and use other tools to complement it. We cost load the schedule to forecas future cash flow and to resource level financial constraints, as I said before detailed history is on the accounting system.

Anyway, good luck with your formulas.  I hope I was of some help.

Best Regards,

Rafael

Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Rafael,

Now I understand the point you are making, which is that Alexandre wants to calculate the efficiency of each resource and this has nothing to do with Baseline which is where BCWS comes in.

I have played around with MS Project and the work around is shown below with explanation of the Custom Fields.

3231
efficiency_01.png

ResName = Text2 with Resource Name pasted into them since I couldn't find a way to access Resource Name in formulas

StandardHrs = Number1 with the formula, IIf([Text2]="R1",(ProjDateDiff([Start],[Status Date],"10-hr / 5-day Week"))/60,IIf([Text2]="R2",(ProjDateDiff([Start],[Status Date],"8-hr / 5-day Week"))/60)) , this calculates the theoretical (standard) hours each Resource should have worked from Actual Start Date to Status Date based on the Resource Calendar

 

3233
efficiency_02.png

ActualHrs = Number2 with the formula, [Actual Work]/60 , this copies the actual hours each Resource has worked from Actual Start Date to Status Date  from the Actual Work field. I copied this to a custom number field so that my calculations will use the same data type (this also assumes you've earlier assigned actual hours for each Resource / day using the Task Usage form)

3226
efficiency_03.png

 

Work Efficiency = Text1 with the formula, Int(([Number2]/[Number1])*100) & "%" , which calculates the Resource Efficiency as at Status Date.

3230
efficiency_04.png

Screenshot below shows final result with other fields (columns) hidden.

3232
efficiency_05.png

It is obvious that this can be set-up quicker in Spider Project compared to MS Project.

 

=jerome
https://plannerstips.blogspot.co.uk/

Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Duplicate -please delete

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Planned work is relative to the schedule version, each represents a plan.  But for P6 Planned Dates are different. The misunderstanding can be an issue of semantics so I made some changes in the hope to make it clear.

  • Baseline Bars [actual/planned] are in yellow, Current Schedule Actual Bars are in grey/blue the other bars represent Current Schedule remaining planned work, you should be able to figure out any date you need from the Gantt, it is a single activity schedule so late and early bars are the same.  

You said - I think you are getting 30 because your formula uses Actual Start Date (07-Dec-15) instead of Baseline Start Date (01-Dec-15) for User Field A.

  • Close, date1=Data Date of current schedule, date2=Start of current schedule, Start is actual if the activity started, is current planned/early start if not started. Of course the dates can be any compatible field you select from current, baseline or compared schedule, can be another computed value.
  • None of my formulas use Baseline Values, but it is possible to create formulas using baseline values when needed.
  • On a full model with all conditions considered:
    • If not started no computation shall be performed 
    • If started but not finished this formula is to be used.
    • If finished then date1=actual finish, date2=actual start.
    • A couple of nested IF statements shall take care of it in a single formula.
Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105
  • On Figure 2 user field is calculated as per formula using a date  and time function, it is the difference un hours between Data Date and Start Date Resource A calendar. Three days at 10hr/day equals 30 hours. This is your key formula I expect MSP can provide. BCWS is calculated using the Baseline, by DD of 12/10/2015 8:00AM it is 50, it has been 50 science end of 5th baseline day.

If Planned Bars are in yellow, figure 2 shows 5 working days so where has the 3 days used in calculating User Field A come from? I expect this to be Diff_Hours_Calen ( #Data Date; Start[Original]; calendar) and with Data Date of 09-Dec-15, Baseline Start Date of 01-Dec-15, should give 50 in User Field A since 07-Dec-15 is the Baseline Finish Date. I think you are getting 30 because your formula uses Actual Start Date (07-Dec-15) instead of Baseline Start Date (01-Dec-15) for User Field A.

I have never used Spider Project so downloaded a demo version to replicate your example but it was hard deciphering how to use it so gave up.

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Are your sure your User Fields autoupdate? 
  • Please take a look at the formula properties it was set up to calculate after every schedule run.
  • You can also take control of which formulas and on what order if using scripts you can record using keystroke recording or the script language. Scripts can also be set up to be run automatically. 
I find it strange that in Figure 2 User Field A is still 30 for Resource A considering that BCWS for Resource A is 50 and at 10 hrs / day,  for us to get BCWS of 50 it means 5 days of Planned Work and as such I expect User Field A to be 50 and not 30.
  • On Figure 2 user field is calculated as per formula using a date  and time function, it is the difference in hours between Data Date and Start Date Resource A calendar. Three days at 10hr/day equals 30 hours. This is your key formula I expect MSP can provide. BCWS is calculated using the Baseline, by DD of 12/10/2015 8:00AM it is 50, it has been 50 science end of 5th baseline day. 
  •  photo HoursFunction_zpsw2o8k2qs.png
Maybe you should show the Planned Start & Planned Finish for both figures so that I can replicate your User Field A calculations.
  • Baseline Planned Bars are in yellow, Actual Bars are in grey/blue the other bars represent current remaining planned work, you should be able to figure out any date you need from the Gantt, it is a single activity schedule so late and early bars are the same.  Planned work is relative to the schedule version.
Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Even with BCWS I don't see why it fails.

Are your sure your User Fields autoupdate? I find it strange that in Figure 2 User Field A is still 30 for Resource A considering that BCWS for Resource A is 50 and at 10 hrs / day,  for us to get BCWS of 50 it means 5 days of Planned Work and as such I expect User Field A to be 50 and not 30.

Maybe you should show the Planned Start & Planned Finish for both figures so that I can replicate your User Field A calculations.

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

The problem is not with ACWP but with BCWS.

  • On the schedule version [1], first figure on my posting:
  • Resource A ACWP for Dec 9  = 27 while BCWS is 30.
  • % = 27/30 = 90%
  • On the schedule version [2], second figure on my posting:
  • Resource A ACWP for Dec 9  = 27 while BCWS is 50.
  • % = 27/50 = 54%

90% is the percentage Alexander is looking for, it is the same on both versions if using as reference the actual work days of the activity instead of the baseline planned work days.

Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Rafael,

I'd expect different results if Actual Start Date = Planned Start Date from if Actual Start Date < > Planned Start Date but not sure this means it fails. So can you please elaborate of the fail aspect.

ACWP calculates cost of Actual Work carried out as at Status Date so does not really matter if Actual Dates differ from Planned Dates, as calculation will only start from first date Actual Work is recorded.




=jerome
http://plannerstips.blogspot.co.uk/

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Not so sure EVM will always yield correct results.

AWL01 photo WorloadampEVM001_zpszrriskny.png

  1. If planned/baseline start and finish matches actual it might do the trick.
  2. As soon as planned/baseline start and/or finish differ actual it fails.

AWL02 photo WorloadampEVM002_zpshztmich7.png

Jerome Odeh
User offline. Last seen 19 hours 21 min ago. Offline
Joined: 19 Jan 2004
Posts: 105

Alexandre,

Yes, MSP can compute the Work Progress at Status Date for you using BCWS & ACWS. Create a text custom field (Work Progress field) and apply the formula = Int(([ACWP]/[BCWS])*100) & "%".

 photo work_chart_zpszvolvjbo.png

 

 photo work_formula_zpsnofeolgn.png

=jerome
http://plannerstips.blogspot.co.uk/
 

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

If what you are looking is to calculate Current Average Workload to compare against planed I believe with use of formulas it can be done.  MSP provides one of the most extensive sets of formulas.

If using Spider the following figure illustrates how it can be done. Of course the formula for C sould be expanded using some nested IF Statements as to consider if Activity is finished, in progress or not started. If using MSP I suspect you might need to use a different view other than Gantt. 

CurrentAverageWorkload photo Actual vs Elapsed Resource Time_zpsnoxwlikp.png

At the beginning I did not see much value on this but after realizing it can be used as to compare planned workload vs current actual I realized its value.

Good luck,

Rafael

Tom Boyle
User offline. Last seen 11 weeks 18 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Regrettably, I don't think you can do what you want through the MSP user interface alone, though with a bit of work you could get the data into Excel and process it there.  (I've manually copied out the task usage table and processed the numbers in Excel - that gets tedious for repeated exercises, however.)

Fundamentally, although "%Complete" and "Cum. %Complete" are available for viewing in the task usage table, these fields get computed and populated only for the tasks, not the individual assignments.  Also remember that these fields are strictly duration-related for a task - they are never earned value.

You are specifically wanting to divide the actual work of each assignment by its baseline work (cumulatively as of a certain date/time.)  For me the main issue lies in the storage (or lack thereof) of time-phased data in MSP, not to mention the weak integration of the "Status Date."  If you had a dire need, then you could develop a vba application to compute and extract the time-phased data from MSP then process it in Excel.  That's not a trivial exercise.    

Good luck, tom