Senior Project Planner, Redis Contstrucion Afrika, Asanko Gold Plant Ghana

START Date: 
November, 2014
END Date: 
August, 2015

• Supervised the Master Program Schedule maintenance including input, revision and updating.
• Prepared and reviewed schedule durations for all disciplines and trade activities relative to the support of project milestones. Calculated durations and other considerations affecting activity durations.
• Calculated critical path for schedule networks and analyzed activities related to progress and adherence to the critical path.
• Implemented WBS resource coding in all schedules.
• Prepared project related correspondence concerning scheduling issues.
• Reviewed and analyzed subcontractor schedule networks.
• Supervised Project Planners assigned to areas of responsibility.
• Monitoring and control of project schedules for proposals, project specific and installation projects.
• Assist the assigned project manager in tracking the project against its baseline schedule.
• Assist the assigned project manager and engineer to develop and implement recovery plans for off-schedule and unanticipated eventualities.
• Participate in the Project Baseline meetings for engineering.
• Participate in project meetings and revise the internal schedule as per conclusions and advice the Team about the impact on the internal schedule as a result of actions/deficiencies.
• Creating of Early and Late S-Curves to track progress.
• Scheduling of arrival and delivery of materials.
• Creating of Organograms as per area specific.
• The Last Planner.

Experience Hours (Planning & Scheduling): 
1250
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
50