Slip / Delay Column

Member for

21 years 8 months

Suggest using Excel to help communicate and develop the formulas.

Slip Formula photo Slipformula_zps2fdff6ee.jpg

It might be you need an additional UDF and formula to calculate Planned Duration depending on the MSP available fields.

Good Luck,

Rafael

Member for

21 years 1 month

Hi thanks for the reply

 

these links seem to deal with the varience from baseline to resheduled position

What Im actually trying to achieve is the traditional slip column you would get in ASTA

i.e. 10 day activity is due to complete on the report date but is only 80%

so the 3 columns would look like

Planned 100 (Pasted into this column from updating project and then undoing)

Actual 80 (manually typed)

Slip -2 days

All without reshedulling

Any ideas?

 

Charlie

Member for

21 years 8 months

Long time I have not used MSP, do not even have a license but maybe this can help:

http://www.projectlearning.net/pdf/I1.1.pdf

http://office.microsoft.com/en-001/project-help/start-variance-fields-H…

http://www.textndata.com/forums/baseline-finish-finish-variance-206769…

http://pm.stackexchange.com/questions/7942/how-to-calculate-execution-v…

Be careful with formulas and the difference between varanace calculated considering only workdays versus variance that also include non-work days.

Good Luck

Member for

21 years 1 month

anyone? is it possible?