Ms project - Actual cost column

6 replies [Last post]
Bala Murugan
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 5 Aug 2013
Posts: 6
Groups: None

Hi all planners,

I am using ms project-2007 for my scheduling works. I have created a schedule with work resource,cost resource and did save baseline. Now i want to change the values in actual cost column of cost resource based on the site progress but when i tried to do so, i got a problem. When i increase the value of actual cost more than that of baseline cost , the duration of the particular activity is also changing.

I increased the actual cost because of more wastage of materials in the particular activity. I didn't spend more manpower or duration.

Is there a way to enter the actual cost without disturbing the duration of the activity?

What am i missing?

Thanks in advance.

Regards,
Ram

Replies

Bala Murugan
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 5 Aug 2013
Posts: 6
Groups: None

Evgeny,

              Yes, you are right. Thanks for your help...

 

Regards,

Bala

           

Evgeny Z.
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Bala,

I do not have project 2007, but I could not reproduce the behavior, described by you with MS Project 2010. The behavior I observed is as follows:

  • It is not possible to change actual cost until activity is 100% complete. The actual cost in this case is calculated by the formula Actual Cost=Activity Cost*%complete
  • After activity is 100% complete, one can change actual cost and it does not change activity duration

Regards.

Evgeny

Bala Murugan
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 5 Aug 2013
Posts: 6
Groups: None

Hi kumar,

             The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.

 

Thanks in advance,

 

Regards,

Bala

Bala Murugan
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 5 Aug 2013
Posts: 6
Groups: None

Hi kumar,

             The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.

 

Thanks in advance,

 

Regards,

Bala

Kumar Baiju
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi bala

 can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.

 

Regards\\

Kumar Baiju
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi bala

 can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.

 

Regards\\