Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Graphical Indicators in MS Project

1 reply [Last post]
Alex M
User offline. Last seen 16 years 6 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 16
Groups: None
Hi,
Hoe do add Graphical indicators that respond to a formula, ie if current finish date is greater than the Baseline Finish, display a red indicator?

Alex

Replies

James Griffiths
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Hi Alex,

In MSP 2000, you click Tools/Customise/Fields. You then choose which of the fields you are working with. The "Graphical Indicators" is at the bottom of the "Customise Fields" window.

HTH.