Specification b/w Main & Sub Contractor

4 replies [Last post]
Shah. HB
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

In back to back contract,Specification related Delays the method stated for analysis eg.Time impact analysis applies to main contractor alone or even sub contractor should follow the same procedure for doing delay analysis

Replies

Shah. HB
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many Thanks Samer. I got it resolved
Samer Zawaydeh
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

There is a clause in FIDIC that calls for the financial records of payment made to subcontractor to works that were paid for by the client to be submitted upon asking for it.

With kind regards,

Samer
Shah. HB
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi

Thanks Samer.Let me check this one out .Anyways we have workshop on this issue
Samer Zawaydeh
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

It depends on the Conditions of the Subcontract agreement. You will need to follow the agreement between the Contractor and the Subcontractor.

With kind regards,

Samer