Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to show gained revenue

2 replies [Last post]
Anel Murguz
User offline. Last seen 6 years 22 weeks ago. Offline
Joined: 19 Jun 2018
Posts: 3
Groups: None

Hi,

I work as a plannner in a big construction company. 

I want to show my boss how we can save/gaive money by planning. 

I have mentioned for example that we can see in a early stage that all extra work is delaying us. And with our baseline we can visualize this and show it to the customer. Also I have showed him how, with the help of code, resources and filter, how we can display the forecast machine hours and also show the actual work. 


But my question is: Is there any way to show how me earn money by planning? For example "we saved 300 000 dollars because we planned correctly"

 

Please help. 

 

Best regards

Replies

Annamalai (Andy) ...
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 19 Jun 2018
Posts: 4
Groups: None

Hi Anel, 

The best representation for what your trying to acheive is via a Cashflow S-Curve. Example below. (Budget vs Actual vs Forecast to Completion)

In your case the Target / Forecast to Completion cummulative value will be less than the Original budget. 

I normally export data from P6 to excel to do the analysis and display charts. 

5694
fig8.gif

 

Hope this helps!!!

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Anel

The way you will save money is by reducing the programme duration and thereby the site overheads.

You can allocate a site cost per day on the overall summary bar and fix it as the baseline ost.

Adjustments to the original programme will either increase or decrease the sumary bar cost which can be compared by two columns in the table.

Trying to reduce costs on each individual task bar will not work.

Best regards

Mike T.