Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to show planned / as buit / and

2 replies [Last post]
duncan burns
User offline. Last seen 13 years 11 weeks ago. Offline
Joined: 29 Aug 2009
Posts: 16
Groups: None

Similar to the last post but i need a step by step guide in the following scenario.

 

I have inherited a project with an Asta easy plan programme ( I don't usually use Asta) The project is delayed and I want to show the Planned as a baseline that does not move,, then the actual as built,, then I want to highlight relevent evenet that have caused delay..

 

Any help please :) thanks

Replies

duncan burns
User offline. Last seen 13 years 11 weeks ago. Offline
Joined: 29 Aug 2009
Posts: 16
Groups: None

Mike,

 

Many thanks I'll find out what version Iv'e got and proceed as you suggest..

 

Thanks again.

 

Duncan

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Duncan

First you need to upgrade the easy plan to v 11 - easy plan does not show criticality so is useless for delay analysis.

The other thing is that if you have both easyplan and v 11 on the same computer they will

corrupt each other so you will nee to put the easy plan on a data stick.

If you can save the easyplan as an XER file you should then be able to open it in either PowerProject or P6.

When you have it as v 11 then you can create a baseline of the original programme using the File - Baseline Manager.

You can then create an as built baseline using the method described in the other thread.

Both baselines can be in the open view together - in fact I think the upper limit is 9 baselines in one view.

You can now impact your events on the live tasks.

Best regards

Mike Testro