Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Is there a way to link one file to another file?

2 replies [Last post]
Yasine Ali
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

Hi everyone,

Was wondering if it is possible to link one programme to a seperate programme (two seperate files)

For example if I have a Pre-Construction programme on one file and I would like to link it to a seperate file which contains the Construction programme.

How would I go about doing this? or is this not possible?

Replies

Yasine Ali
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

Hi Mike,

Thank you for your input, helpful as always.

Regards

Yas.

Mike Testro
User offline. Last seen 23 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Yasine

Just copy paste the Pre Construction file onto the Construction Programme and turn them both into "Is A Project".

You can then link them at any level and display any views of the two files on one display.

in effect you can have any number of projects in the one file and you can then display the RAG dots for the whole company.

You can also resource level key resource elements across the whole work force on every project.

Best regards

Mike T.