its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.
as Tony said restore the baseline open both projects together then export
Member for
15 years
Member for15 years
Submitted by Alida Prinsloo on Fri, 2015-01-16 11:34
In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.
Member for
16 years 3 monthsits alwasy a good practice to
its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.
as Tony said restore the baseline open both projects together then export
Member for
15 yearsP { margin-bottom: 0.21cm;
P { margin-bottom: 0.21cm; }A:link { }
Good Day All,
I am currently working on Primavera 6 version 8.1. I there a option to export the project baseline and the current execution schedule altogether? If the there is now other way. I guess the only why is to release the project baseline and restore the baseline and to export both the exceution schedule and the baseline.
What are your thougths out there?
Kind Regards,
Alida
Member for
17 years 1 monththanks Tony for your
thanks Tony for your illustration
Member for
13 yearsHow to use refliction? syed
How to use refliction?
syed
Member for
15 yearsuse refliction in P6 it will
use refliction in P6 it will include current schedule along with more than one baseline.
Essam
Member for
12 years 8 monthsIn the maintain baselines
In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.