Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hide Bar

9 replies [Last post]
Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Dear experts/Mike

Please mention the steps that 

1) How to hide bar under shaded timescale?

2) How to show the full summary bar instead of break in summary?

Please see snapshot for 1 and 2 : http://ge.tt/3OBWrnl2

I used all options but no success.

I tried Format bar chart>non working >uncheck/check>on tasks>on allocations but problem not solved. Snapshot would be great help

Cheers

Replies

Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Thanks Mike

Mike Testro
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Andy - sorry for the late response but I had some deadlines to meet.

What you have shown is the task bar sitting over the holiday period which is the normal view.

The tasks start and end over the holiday period but the working days will remain the same duration - this is completely normal.

You can set the view so that the holiday shading sits over the bar using >Format > Barchart > Non Working - and select required display.

Or you block out the holiday completely in the same dialogue.

Best regards

Mike T.

Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Mike may be busy.

Some other expert asta user also in this forum being asta is leading softwrare. Asta support people also visiting the forum.

No one have answer of it.. Strange ???? 

 Can someone solve this issue please?

cheers,

Andy

Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Sorry Mike

Check now please

http://imgur.com/a/m0e4J

Need to move part of bar 11 ans 12 showing on shaded timescale .

Thanks,

Mike Testro
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Andy

Can't open it.

You need to work out how to put an image on PP.

Rafael Davila is an expert.

Best regards

Mike T.

Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

 

4882
bar.png
Hi Mike 

Here is the image

Regards,

Andy 

Mike Testro
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Andy

Link does not work

Best regards

Mike Testro

Andy Hudson
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Hi Mike,

Thanks for replying.

Necking problem has been solved.

But Bar no 11 is still on shaded timescale where the part of that bar showing in orange/red highlighted in screenshot- http://ge.tt/2aq3Kol2)  coming on shaded holidays timescale, must start after holidays

My question is that what steps I need to follow so Orange/red part showing on shaded timescale must start after holidays timescale automatically?

Regards,

Andy

Mike Testro
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Andy

You are displaying the P6 replica view with necking.

The stanard powerproject view is a simple straight bar - just disable the necking facility.

To simply hide a bar from view then Right click on task > Properties > select for hiding> In the format ribon click the Hide icon.

Best regards

Mike Testro