Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hide Activities in Asta

2 replies [Last post]
Bill Joshaf
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 27 Jun 2005
Posts: 33
Groups: None
Any Asta expert can tell me the tips that how to hide the specific activities in Asta? I used these options to hide the specific activities.
Hide and show the toolbar and Mark for hiding
but no result.
Any idea?


Replies

Bill Joshaf
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 27 Jun 2005
Posts: 33
Groups: None
Hi Mike
Thanks for your prompt response. Its really good tip.
Mike Testro
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Bill

In version 10 select the bar and right click on the task for the task drop down.

Left click on the "Mark for Hiding" option.

Repeat for all other tasks.

In the Format drop down click Hide Marked Items.

The marked tasks disapear.

Best regards

Mike Testro